TM 9-2320-364-10
2-62
Table 2-1. Operators Preventive Maintenance Checks
and Services (Before) - CONT.
Location
Item
No.
Interval
Item to
Check/
Service
Procedure
Not Fully Mission
Capable if:
NOTE
Make the following check if the Material Handling Crane (MHC) is
installed.
6
Before
Material
Handling
Crane
(MHC)
Check crane (1) for obvious
damage and loose parts. Check
left and right outrigger jacks (2)
and valve banks (3) for damage,
leaks, missing and loose parts.
Check if MHC MAIN
HYDRAULIC PRESSURE
MANUAL OVERRIDE
valve (4) is pushed in and locked.
Check that safety wire and seal (5)
are present on MHC SYSTEM
HYDRAULIC PRESSURE
MANUAL OVERRIDE button (6).
Class III leak is
evident. Crane is
damaged or parts are
missing.
|