TM 9-2320-364-10
2-78
Table 2-1. Operators Preventive Maintenance Checks
and Services (Before) - CONT.
Location
Item
No.
Interval
Item to
Check/
Service
Procedure
Not Fully Mission
Capable if:
Check for overhead power lines or other obstructions before
attempting LHS operation. LHS reaches a height of 17 ft. two in.
(5.22 m) with ISO container. Serious injury or death could result
from contact with electrical power lines.
15
Before
Load
Handling
System
(LHS)
Controls
(a) Check for proper operation of
hydraulic selector switch (1) and
joystick control (2). Verify by
placing hydraulic selector
switch (1) in the AUTO position.
LHS will not
operate.
(b) Pull joystick (2) to rear to raise
LHS approximately one to two ft.
(0.305 to 0.609 m). LHS light (3)
will light green and LHS NO
TRANS light (4) will light red.
LHS OVERLOAD light (5) may
light yellow if system is
overloaded.
(c) Push joystick (2) forward and
lower to transport position. LHS
NO TRANS light will go out.
|