TM 9-2320-364-34-2
12-43
(8)
At right front of suspension beam hanger, hold plumb-bob from inside machined surface of suspension
beam hanger straight down to floor and scribe mark on floor.
(9)
At right rear of suspension beam hanger, hold plumb-bob from inside machined surface of suspension
beam hanger straight down to floor and scribe mark on floor.
(10)
Repeat Steps (5) through (9) for left side of front tandem axles and suspension beam hanger.
(11)
Distance A (left side) measurement should equal distance B (right side) measurement within a tolerance
of 1/8 in. (3.18 mm) for both Axles No. 1 and 2.
(12)
If distance between A and B is not equal within tolerances, add or subtract spacers on lateral torque rods,
(Para 14-8).
(13)
If spacers are added or subtracted, it will be necessary to repeat Steps (1) through (12).
|