TM 9-2320-364-34-2
10-2
Materials/Parts
Rags, Wiping (Item 47, Appendix B)
Sealing Compound (Item 56, Appendix B)
Tape, Masking (Item 73, Appendix B)
Locknut (15) (Item 216, Appendix E)
This task covers:
a. Axles No. 1, 2 and 5 Replacement b. Axles No. 3 and 4 Replacement c. Follow-On Maintenance
INITIAL SETUP
Personnel Required
Two
Equipment Condition
Engine OFF, (TM 9-2320-364-10)
Wheels chocked, (TM 9-2320-364-10)
Oil drained from axle, (TM 9-2320-364-20)
Brake drum removed, (TM 9-2320-364-20)
Planetary hub gear removed, (Para 9-6)
Wheel hub assembly removed, (Para 11-2)
Air chamber(s) removed, (TM 9-2320-364-20)
Tools and Special Tools
Tool Kit, General Mechanics
(Item 240, Appendix F)
Adapter, Socket (3/4 in. female to 1/2 in. male)
(Item 9, Appendix F)
Jack, Hydraulic, Hand (Item 128, Appendix F)
Respirator, Air Filter (Item 195, Appendix F)
Socket, Socket Head Screw 14 mm
(Item 207, Appendix F)
Wrench Set, Socket 3/4 In. Drive
(Item 274, Appendix F)
Wrench, Torque (0 to 600 lb-ft [0-814 N.m])
(Item 278, Appendix F)
Lifting Device, Minimum Capacity 100 lbs
(45 Kg)
10-2. AXLE BRAKE ASSEMBLY REPLACEMENT.
|