TM 9-2320-364-34-3
16-181
(6)
Apply hydraulic oil to preformed
packing (98) and backup ring (97).
(7)
Install two preformed packings (98) and
backup ring (97) on each of three check
valves (96).
(8)
Install three check valves (96) in
manifold (34).
(9)
Apply hydraulic oil to three preformed
packings (95).
(10)
Install three preformed packings (95) and
plugs (94) in manifold (34). Tighten plugs
to 55 to 65 lb-in (6 to 7 N.m).
(11)
Apply hydraulic oil to preformed
packings (93), (92), (91) and (90).
(12)
Install preformed packings (93), (92), (91)
and (90) in manifold (34).
(13)
Apply hydraulic oil to two preformed
packings (89) and backup rings (88).
(14)
Install two preformed packings (89) and
backup rings (88) on check valve (87).
(15)
Install check valve (87) in hoist/lift
manifold (8).
(16)
Apply hydraulic oil to preformed
packings (85) and (86).
(17)
Install preformed packings (86) and (85) and
plugs (84) and (83) in hoist/lift manifold (8).
|