TM 9-2320-364-20-4
5-10
Material/Parts
Clamp (Item 12, Appendix F)
Clamp (2) (Item 18, Appendix F)
Locknut (Item 92, Appendix F)
This task covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Equipment Condition
Engine OFF, (TM 9-2320-364-10)
Wheels chocked, (TM 9-2320-364-10)
Spare tire removed, (TM 9-2320-364-10)
Right side noise panel removed, (Para 17-26)
Engine cover opened, (TM 9-2320-364-10)
Tools and Special Tools
Tool Kit, General Mechanics: Automotive
(Item 74, Appendix G)
Wrench, Torque (0 to 60 N.m)
(Item 98, Appendix G)
5-3. EXHAUST PIPES REPLACEMENT.
a.
Removal.
Ensure this task is done only when muffler is cool. Performing this task on a warm or hot
muffler may result in severe burning to personnel.
(1)
Remove and discard locknut (1) and clamp (2) from exhaust pipe (3) and turbocharger (4).
|