TM 9-2320-364-20-5
21-206
21-41. CONTAINER HANDLING UNIT (CHU) BUMPER WELDMENT
REPLACEMENT (CONT).
NOTE
Shims may or may not be
present in Step (3).
Note number of shims prior
to removal.
(3)
Remove two locknuts (6), shim(s) (7) and
two bumpers (8) from bumper weldment (2).
Discard locknuts.
NOTE
Perform Step (4) only if wire rope
is damaged.
(4)
Remove two swaging sleeves (9) and wire
rope (10) from bumper weldment (2) and
snapper pin (1).
b.
Installation.
NOTE
Left and right bumper
weldments are identical.
Right bumper weldment is
shown.
Perform Steps (1) and (2)
only if wire rope was
removed.
(1)
Position wire rope (10) through hole of
bumper weldment (2).
(2)
Install two swaging sleeves (9) and wire
rope (10) on snapper pin (1) and bumper
weldment (2).
NOTE
Install shims as noted prior to
removal.
(3)
Install two bumpers (8), shim(s) (7) and two
locknuts (6) on bumper weldment (2).
6
7
10
9
8
9
2
HOLE
1
|