TM 9-2320-364-34-2
9-28
Materials/Parts
Wire (Item 78, Appendix B)
This task covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Personnel Required
Two
Equipment Condition - Continued
Shift transfer case to low,
(TM 9-2320-364-10)
Switch CTIS switch to EMERGENCY,
(TM 9-2320-364-10)
Drive truck forward or backward,
(TM 9-2320-364-10)
Engine OFF, (TM 9-2320-364-10)
Wheels chocked, (TM 9-2320-364-10)
Wheels/tires removed, (TM 9-2320-364-10)
Locking cylinder removed, (Axle No. 3
Para 9-17 or Axle No. 4 Para 9-16) (If
removing left side axle shaft only)
Axle oil drained, (TM 9-2320-364-20)
Planetary hub gears removed, (Para 9-6)
Tools and Special Tools
Tool Kit, General Mechanics
(Item 240, Appendix F)
Jackstand (Item 132, Appendix F)
9-5. AXLE NO. 3 AND 4 AXLE SHAFT REPLACEMENT.
Equipment Condition
(Perform the first five equipment conditions only
if removing left side axle shaft)
Start engine, (TM 9-2320-364-10)
Build up air pressure to 125 psi (862 kPa),
(TM 9-2320-364-10)
|