TM 9-2320-364-34-3
15-17
(10)
With the aid of an assistant and using lifting device, lower cab (27) and position two washers (136) and
locknuts (135) on screws (137).
(11)
Remove wooden blocks, lifting device, guide rope and cable ties from cab (27), doors (139) and grab
handles (140).
(12)
With the aid of an assistant, install two screws (137) with locknuts (135).
(13)
With the aid of an assistant, install two screws (147) with locknuts (145).
NOTE
Step (14) applies to left side of truck only.
(14)
Install ground strap (142) on cab (27) with screw (143) and locknut (141).
Rust preventive contains alkali. Do not get in eyes. Wear goggles/safety glasses when using
rust preventive. Avoid contact with skin. In case of contact with rust preventive, immediately
wash area with soap and water. If rust preventive contacts eyes, flush eyes with large amounts
of water for at least 15 minutes and get immediate medical attention.
(15)
Coat connection at ground strap (142), with corrosion preventive compound.
|