TM 9-2320-364-34-3
16-57
Materials/Parts
Grease (Item 21, Appendix B)
This task covers:
a. Adjustment
b. Follow-On Maintenance
INITIAL SETUP
Personnel Required
Two
Equipment Condition
Crane erected, (TM 9-2320-364-10)
Engine OFF, (TM 9-2320-364-10)
Wheels chocked, (TM 9-2320-364-10)
Tools and Special Tools
Tool Kit, General Mechanics
(Item 240, Appendix F)
Wrench Set, Socket 3/8 in. Drive
(Item 273, Appendix F)
Wrench, Torque (0-60 N.m)
(Item 276, Appendix F)
16-4. BOOM CABLE AND CHAIN ADJUSTMENT.
a.
Adjustment.
(1)
Remove four screws (1), washers (2) and cover (3) from boom base (4).
|