TM 9-2320-364-34-3
16-77
(5)
Apply hydraulic oil to preformed packings
(6) and (7).
(6)
Install preformed packings (6) and (7) and
connect hoses (2) and (3) on tubes (4)
and (5).
NOTE
Install cable ties as required.
(7)
Secure overload shutdown connector (9) to
tube (5) with cable ties.
(8)
Lower mast (1) into installed position and
remove lifting device.
c.
Follow-On Maintenance:
Install lift cylinder, (Para 16-6).
Install boom assembly, (Para 16-3).
Lubricate crane, (TM 9-2320-364-20).
Load test crane, (Para 16-32).
Remove wheel chocks, (TM 9-2320-364-10).
END OF TASK
|