This task covers:
a. Alignment
b. Follow-On Maintenance
INITIAL SETUP
Tools and Special Tools
Personnel Required
Tool Kit, General Mechanic's
Two
(Item 49, Appendix J)
Materials/Parts
Jack (Item 22, Appendix J)
Chalk, Marking White (Item 9, Appendix E)
Jack, Stabilizer (2) (Item 23, Appendix J)
Jackstand (2) (Item 24, Appendix J)
Equipment Condition
Plumb Bob (Item 33, Appendix J)
Wheels chocked, (Para 2-20)
Socket Set, 1 in. (Item 38, Appendix J)
Drawbar level, (Para 2-23)
Socket Set, 3/4 in. (Item 39, Appendix J)
Tape Measurer (Item 47, Appendix J)
Wrench, Impact Electric (Item 59, Appendix J)
(Item 62, Appendix J)
a.
Alignment.
(1)
Using a jack, raise rear of trailer (1) and support on two jackstands under suspension hanger assembly (2)
so rear tires (3) are off ground.
(2)
Refer to Para 4-57 and remove rear wheels (3) from Axle No. 2 (4) and Axle No. 3 (5).
|