l)
Locate the Strap Assembly attachment point on the top of the door frame as shown in
Figure 29.
m) Mark the location of the Strap Assembly attachment point using a center punch and
hammer.
n) Using a drill and a 3/16-in. drill bit, drill a pilot hole though one side of the door pillar
tubing in the marked position.
o) Drill through the pilot hole with a series of drill bits until a final hole size of 17/32-in
diameter is in the door pillar.
p) Install the Strap Assembly to the door pillar using one bolt (3/8 16 x 3.000 LG), two
washers (3/8 ID), and two flange bushings (P/N 1114111-1), one on each side of the
tube, and one locknut (3/8 16) torqued to 10 ft-lb (see Figure 29).
q) Install the Door Striker Base and Striker Pin, as shown in Figure 26.
r) Locate and mark the holes for the Door Striker Support using a center punch and a
hammer, as shown in Figure 27. The Door Striker Support should butt up against the
bottom edge of the Door Striker Base, adjust as required.
s) Using a drill and a 3/16-in. drill bit, drill a pilot hole though one side of the door pillar in
the positions that were marked.
t)
Using a drill and a 17/32-in drill bit, drill through the pilot holes in the door pillar.
u) Install two Rivnuts (0.312-18 X 0.027-0.150 Grip) using the Rivnut Installation Tool (see
Table 16).
v) Attach the Door Striker Support (P/N 113327-1), as shown in Figure 26, using two
0.312-18 x 1.00 Long Cap Head Bolts.