6.
If the BAP is loaded, inspect load and make sure it is secure.
CAUTION
The BAP holddown locks must be unlocked from the LHS prior to starting BAP unloading
operations. Failure to comply may result in damage to equipment.
7.
Release BAP holddown locks by pulling handle out (Figure 3, Item 5).
5
SHOWN WITHOUT BAP
INSTALLED FOR CLARITY
Figure 3. Release BAP Hold Down Locks.
CAUTION
The BAP is front-heavy. Arrange cable length accordingly. Failure to comply may result in
damage to equipment.
8.
With the aid of an assistant, the crane operator secures four-legged sling to BAP lifting eyes (Figure 4, Item
6) and to crane or other materiel handling-system hook.