TM 5-3990-263-13&P
OPERATOR MAINTENANCE
MANUALLY LOADING BRIDGE ADAPTER PALLET (BAP) FROM THE GROUND
INITIAL SETUP:
Personnel Required
References
(2)
PERFORM PROCEDURE
NOTE
The following manual mode operations using the cab control box are to be performed only
1.
Secure winch frame to the BAP. Ensure two winch frame locking levers (Figure 1, Item 1) are in the up position.
1
2
Figure 1. Secure Winch Frame to BAP.
2.
If locking levers (Figure 1, Item 1) are not up:
a.
Remove lockpin (Figure 1, Item 2) from each locking lever (Figure 1, Item 1).
b.
Swing locking lever (Figure 1, Item 1) to the up position.
c.
Insert lockpin (Figure 1, Item 2) into locking lever (Figure 1, Item 1).
3.
If the BAP is loaded, inspect load and ensure it is secure.
03/15/2011Rel(1.8)root(opunuwp)wpno(O01050)