CAUTION
Do not position PTO ENGAGE switch to ON with HIGH IDLE switch ON. Engaging the
PTO with HIGH IDLE switch ON may result in sudden application of hydraulic pressure
to the LHS. Failure to comply may result in damage to equipment.
PTO ENGAGE switch must be positioned OFF before road transport. Failure to comply
may result in damage to equipment.
10.
Set PTO ENGAGE switch (Figure 5, Item 9) to ON position. Indicator light (Figure 5, Item 10) will illuminate.
10
12
9
JACO
B
S
7
ENGIN
E
BRAK
E
ANALOG CBT CONTROL PANEL
CAUT
ION
XHA
OE U
ILER Y
TRA PILG
RSUPND
N
AIOTFORPARK
LA
MID
N
US
HTO
13
19
11
5
6
19
18
11
16
15
13
17
DIGITAL CBT
CONTROL PANEL
14
17
Figure 5. Manually Unload BAP to the Ground.
11.
Turn LHS MODE SELECT switch (Figure 5, Item 11) to MAN HOOK ARM.
12.
Set HIGH IDLE switch (Figure 5, Item 12) to ON position.